Posted information is for planning purposes only. For the most up to date closure information please refer to the
FAA NOTAM
system
Taxiway Activity
Runway Activity
Show All
Terminal/Gate Activity
Other Activity
< Prev
Today
Next >
March
2025
Last Updated: 2025-03-15 0:31
SUNDAY
MONDAY
TUESDAY
WEDNESDAY
THURSDAY
FRIDAY
SATURDAY
1
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
2
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
3
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
5:30 Gate 68B Closed for fuel low point installation
4
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
5
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
6
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
7
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
8
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
9
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
10
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
11
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
12
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
13
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
14
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
15
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
1:30-5:00 Gate 43 Closure- Trash service
16
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
1:30-5:00 Gate 43 Closure- Trash service
17
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
0:00-6:00 TBIT Gate 148
0:30-6:00 Gate 53B Closure
1:30-5:00 Gate 43 Closure- Trash service
18
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
0:00-6:00 TBIT Gate 141
0:00-6:00 Terminal 4 Gate 46A (behind construction barricade)
0:00-6:00 Terminal 5 Gate 56A
1:00-6:00 Gate 148 Hard Closure LADWP
1:30-5:00 Gate 43 Closure- Trash service
19
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
0:00-6:00 Terminal 4 Gate 46A (behind construction barricade)
0:00-6:00 Terminal 5 Gate 56A
1:30-5:00 Gate 43 Closure- Trash service
20
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
0:00-6:00 Terminal 6 Gate 66 & Bus loop
0:00-6:00 Terminal 5 Gate 56A
1:30-5:00 Gate 43 Closure- Trash service
21
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
0:00-6:00 Terminal 6 Gate 66 & Bus loop
0:00-6:00 Terminal 5 Gate 56A
1:30-5:00 Gate 43 Closure- Trash service
22
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
1:30-5:00 Gate 43 Closure- Trash service
23
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
1:30-5:00 Gate 43 Closure- Trash service
24
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
0:00-6:00 Terminal 6 Gate 66 & Bus loop
0:00-6:00 Terminal 7 Gate 74
0:30-3:00 Terminal 7 - Gate 70B - Hard Closure
1:30-5:00 Gate 43 Closure- Trash service
25
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
0:00-6:00 Terminal 6 Gate 66 & Bus loop
0:00-6:00 Terminal 7 Gate 74
1:30-5:00 Gate 43 Closure- Trash service
26
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
1:30-5:00 Gate 43 Closure- Trash service
27
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
Gate 68B Closed for fuel low point installation
0:00-6:00 Terminal 6 Gate 66 & Bus loop
1:30-5:00 Gate 43 Closure- Trash service
28
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
0:00-16:30 Gate 68B Closed for fuel low point installation
0:00-6:00 Terminal 6 Gate 66 & Bus loop
1:30-5:00 Gate 43 Closure- Trash service
29
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
1:30-5:00 Gate 43 Closure- Trash service
30
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
1:30-5:00 Gate 43 Closure- Trash service
31
Gate 40
Phase 2 - Gates 42B, 46A, 45, 47, & 49A
0:00-6:00 Terminal 4 Gate 646A (behind construction barricades)
0:00-6:00 Terminal 5 Gate 56A
1:30-5:00 Gate 43 Closure- Trash service